Cambria Community Services District Wastewater Treatment Plant Upgrades
Cambria, CA
Upgrading wastewater treatment to meet future nitrogen discharge limits
Ardurra completed the final design and Engineering Services During Construction (ESDC) for approximately $12 million in upgrades to the Cambria Community Services District Wastewater Treatment Plant. Beginning with a Basis of Design Report, the project was driven by future total nitrogen discharge limits and required a full process conversion within a continuously operating coastal facility.
Key Highlights:
-
Converted the existing activated sludge system to a Modified Ludzack-Ettinger (MLE) process, significantly improving nitrogen removal efficiency
-
Upgraded aeration basins with new mixers, diffusers, instrumentation, and scum handling systems
-
Constructed a new flow equalization basin and pump station, and installed a shared blower system
-
Upgraded the influent lift station with grit system modifications and installed a new RAS/WAS pump station
-
Developed construction sequencing strategies to maintain full plant operations, including bringing new flow equalization facilities online early to minimize transition impacts
The upgrades position the Cambria WWTP for long-term regulatory compliance, protect downstream coastal ecosystems, and extend the facility's useful life while maintaining uninterrupted service to the community throughout construction.
Project Information & Awards
Market
Water/Wastewater, Civil, Public Works
Client
Cambria Community Services District
Delivery Method
Design-Bid-Build
Services
- Preliminary & Final Process Design
- Basis of Design Report
- Wastewater Treatment Plant Engineering
- Engineering Services During Construction (ESDC)
- Construction Sequencing & Operational Coordination