Meeker Airport Coulter Field Runway and Apron Reconstruction
Meeker, CO
$13.5 million C-II runway and apron reconstruction with land acquisition
Ardurra's aviation group delivered runway and apron reconstruction services for Coulter Field's $13.5 million infrastructure modernization project, encompassing the full spectrum of airport engineering and management expertise. The transformative project included the complete reconstruction of Runway 3/21 and the apron area to meet enhanced C-II standards, enabling safe operations for larger class aircraft frequenting the facility.
The scope included demolition of existing runway infrastructure and reconstruction meeting C-II runway safety area standards and longitudinal gradient requirements. Strategic design coordination enabled the concurrent construction of the new runway, an enlarged aircraft apron, and a partial parallel taxiway connecting both facilities, while maintaining operational continuity.
Key Project Achievements:
-
Completed $13.5 million runway and apron reconstruction, upgrading Coulter Field to C-II standards, accommodating larger aircraft operations
-
Demolished and reconstructed Runway 3/21, meeting enhanced runway safety area and longitudinal gradient standards
-
Expanded apron infrastructure to C-II standards, enabling safer handling of larger class aircraft frequenting the airport
-
Constructed a partial parallel taxiway connecting the new runway and enlarged apron facilities for enhanced operational efficiency
-
Replaced the complete lighting system with new signage and NAVAIDs supporting modern aviation safety and operational requirements
-
Acquired 107 acres of land through strategic coordination with county officials, landowners, and airport tenants
-
Managed concurrent construction activities, maintaining airport operations while delivering comprehensive infrastructure improvements
The reconstruction provides Meeker with modern aviation infrastructure supporting enhanced aircraft operations and regional connectivity. Strategic land acquisition and phased construction approaches enabled infrastructure expansion while maintaining essential aviation services throughout the modernization process.